Reference project in Müllekoven

Two belt thickeners and a polymer preparation station as part of the expansion of the Müllekoven wastewater treatment plant

As part of the expansion of the Müllekoven wastewater treatment plant, Abwasserbetrieb Troisdorf AöR placed an order with SÜLZLE KLEIN at the beginning of 2020 for the supply of two customized belt thickeners and a polymer preparation station. The aim was to upgrade the mechanical excess sludge thickening to increase the energy efficiency of the plant. By working in partnership with all parties involved in the project, SÜLZLE KLEIN was able to offer an innovative and equally efficient solution. A major advantage of the solidXdrain mobile belt thickener system was that the wastewater treatment plant was able to maintain operation “24/7” throughout the entire installation period. After smooth delivery in August 2020 and on-time commissioning one month later, nothing stood in the way of successful acceptance in October 2020. The throughput of the new plant per line/thickener is 5-25 m³/h and meets all the required performance data and corresponds to the latest state of the art.

Whether by phone, e-mail or contact form: We look forward to your enquiry.

Do you have questions about our products and services or need further information? Our experts are happy to help you. You can reach us by phone from Monday to Friday between 8:00 am and 5:00 pm. Or write to us – by post, e-mail or conveniently via our contact form. We look forward to hearing from you!

Our experts are happy to be there for you. Don’t hesitate and feel free to call us or write to us – by post, e-mail or conveniently via our contact form. We look forward to hearing from you!

Facts and figures about the project:

84.000

Population equivalents

5 %

Solids content in thickened sludge

525 m³/h

Throughput of the new plant per line/thickener

September 2020

Commissioning